Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.43 | 7.43 | 0.000 | 7.43 | 7.430 | 7.430 |
37W489 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
131.55
Resanction Cost :
131.55
Tentative Cost :
131.55
Exp. Upto Last Fy : 36.16
For CFY 2024-2025
Remaining : 95.39
Demand : 100.39
Allotment : 65.25
Exp in CFY : 65.23
Total Up to Date Exp : 101.39
Work completed
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 2 weeks from now
02 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 14-Jun-2024
Physical Peramenters