Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 25.66 | 21 | 0.000 | 21 | 21.000 | 4.000 |
37W490 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
345.46
Resanction Cost :
345.46
Tentative Cost :
345.46
Exp. Upto Last Fy : 0.57
For CFY 2024-2025
Remaining : 344.89
Demand : 250.00
Allotment : 45.25
Exp in CFY : 45.25
Total Up to Date Exp : 45.82
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 25 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 16-Dec-2023
Physical Peramenters