Work Profile

जनपद चमोली के विधानसभा क्षेत्र थराली के अन्तर्गत नारायणबगड़-कर्णप्रयाग मोटर मार्ग किमी0 3 किमोली मोटर मार्ग।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : पत्र सं0- 895/07याता0-पी0एम0जी0एस0वाई0-नि0 ।।। दिनांक 16.05.2023

TS Amount (lakhs) : 0 Lacs

Financial Detail

Sanction Cost : 113.29 Lacs

Resanction Cost : 113.29 Lacs

Exp. Upto Last Fy : 47.61 Lacs

For CFY 2024-2025

Remaining : 65.68 Lacs

Demand : 65.60 Lacs

Allotment : 30.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 47.61 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 15 %

Up to Date : 15 %

Sanction on :
1 year 3 days ago
16 May 2023


Tentative Completion date:
4 months 5 days from now
25 Sep 2024


Actual Completion Date:
Not Yet Reported


Rating : 76

Remark

Bottelneck: no issue


कार्य प्रगति में। -- as on 13-Dec-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 19.94 19.94 0.000 19.94 0.000 0.000