Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.35 | 0.35 | 0.350 | 0 | 0.000 | 0.000 |
37W494 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मुख्य विकास अधिकारी, चमोली का पत्रांकः- 225/जि0यो0/2023-24 दिनांक 01.06.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5.00
Resanction Cost :
5.00
Tentative Cost :
5.00
Exp. Upto Last Fy : 3.50
For CFY 2024-2025
Remaining : 1.50
Demand : 1.50
Allotment : 1.50
Exp in CFY : 0.00
Total Up to Date Exp : 3.50
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
01 Jun 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 30-Mar-2024
Physical Peramenters