37W502 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मुख्य विकास अधिकारी, चमोली का पत्रांकः- 225/जि0यो0/2023-24 दिनांक 01.06.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
8.50
Resanction Cost :
8.50
Tentative Cost :
8.50
Exp. Upto Last Fy : 6.85
For CFY 2024-2025
Remaining : 1.65
Demand : 1.65
Allotment : 1.15
Exp in CFY : 0.33
Total Up to Date Exp : 7.18
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
1 year 1 month ago
01 Jun 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 25-Nov-2023
Physical Peramenters