Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.31 | 6.31 | 0.000 | 6.31 | 0.000 | 0.000 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
37W512 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या:- 48456 लोक निर्माण अनुभाग-2 देहरादून दिनांक 21.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 103.50 Lacs
Resanction Cost : 103.50 Lacs
Exp. Upto Last Fy : 13.28 Lacs
For CFY 2024-2025
Remaining : 90.22 Lacs
Demand : 90.22 Lacs
Allotment : 40.00 Lacs
Exp in CFY : 27.74 Lacs
Total Up to Date Exp : 41.02 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
8 months 4 weeks ago
21 Aug 2023
Tentative Completion date:
2 months 1 week from now
02 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 13-Dec-2023
Physical Peramenters