Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.38 | 8.38 | 0.000 | 8.38 | 8.380 | 8.380 |
Jobs | 1 | 0 | 0 | 0 | 0 |
37W515 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या:- ई-पत्रावली संख्या-48456 लोक निर्माण अनुभाग-2 देहरादून दि0 10.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
141.25
Resanction Cost :
141.25
Tentative Cost :
141.25
Exp. Upto Last Fy : 38.66
For CFY 2024-2025
Remaining : 102.59
Demand : 102.59
Allotment : 69.22
Exp in CFY : 69.21
Total Up to Date Exp : 107.87
Work completed
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 14-Jun-2024