Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 17.5 | 17.5 | 0.000 | 17.5 | 0.000 | 0.000 |
37W526 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या:- 5082/।।।(2) /2023-01 (प्रा0आ0)/ 2023 दिनांक 09.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 327.59 Lacs
Resanction Cost : 327.59 Lacs
Exp. Upto Last Fy : 100.19 Lacs
For CFY 2024-2025
Remaining : 227.40 Lacs
Demand : 227.40 Lacs
Allotment : 100.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 100.19 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
6 months 1 week ago
09 Nov 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 30-Mar-2024
Physical Peramenters