Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 52.2 | 52.2 | 0.000 | 52.2 | 0.000 | 0.000 |
37W527 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या- 5082/।।।(2) /2023-01 (प्रा0आ0)/2023 दिनांक 09.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 167.70 Lacs
Resanction Cost : 167.70 Lacs
Exp. Upto Last Fy : 53.86 Lacs
For CFY 2024-2025
Remaining : 113.84 Lacs
Demand : 113.84 Lacs
Allotment : 70.00 Lacs
Exp in CFY : 88.64 Lacs
Total Up to Date Exp : 142.50 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
6 months 1 week ago
09 Nov 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 30-Mar-2024
Physical Peramenters