Work Profile Report [37W530]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-पत्रावली संख्या-44379/06 लोक निर्माण अनुभाग-2 देहरादून दिनांक 19.01.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
222.12
Resanction Cost :
222.12
Tentative Cost :
222.12
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
222.12
Demand :
75.00
Allotment :
54.55
Exp in CFY :
40.60
Total Up to Date Exp :
40.60
Construction Started
Sanction on : 11 months 5 days ago
19 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
50 %
Tentative Completion date on : 5 months 1 week from now
05 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कलवर्ट, जी01,जी02,जी03 का कार्य प्रगति में। -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand