Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.4 | 2.4 | 0.000 | 2.4 | 0.000 | 0.000 |
37W530 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली संख्या-44379/06 लोक निर्माण अनुभाग-2 देहरादून दिनांक 19.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
222.12
Resanction Cost :
222.12
Tentative Cost :
222.12
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 222.12
Demand : 75.00
Allotment : 27.00
Exp in CFY : 26.56
Total Up to Date Exp : 26.56
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 30 %
Sanction on :
5 months 4 weeks ago
19 Jan 2024
Tentative Completion date:
10 months 2 weeks from now
05 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 30-Mar-2024
Physical Peramenters