Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
37W531 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-पत्रावली संख्या-60147 संख्या 178856/IX/23-01(01)/2023 नागरिक उड्डयन अनुभाग देहरादून दिनांक 01.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
99.49
Resanction Cost :
99.49
Tentative Cost :
99.49
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 99.49
Demand : 94.49
Allotment : 59.69
Exp in CFY : 33.02
Total Up to Date Exp : 33.02
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 34 %
Sanction on :
6 months 2 weeks ago
01 Jan 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 30-Mar-2024
Physical Peramenters