Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 2 | 2 | 0 |
38W201 :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Chtawapipal Suspension Bridge Over Alaknanda River
Administrative Approval Detail : 337/।।।(2)/09-43(प्रा0आ0)/09 दि0 12.3.10
TS Amount (lakhs) : 166.55 Lacs
Financial Detail
Sanction Cost : 183.75 Lacs
Resanction Cost : 183.75 Lacs
Exp. Upto Last Fy : 183.72 Lacs
For CFY 2024-2025
Remaining : 0.03 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.03 Lacs
Total Up to Date Exp : 183.74 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 98 %
Up to Date : 98 %
Sanction on :
14 years 3 months ago
12 Mar 2010
Tentative Completion date:
8 months 4 weeks from now
31 Mar 2025
Actual Completion Date:
1 year 3 months ago
01 Apr 2023
Remark
Forest Status 21: Final
Bottelneck: no issue
वन भूमि की विधिवत स्वी. शा.सं. एक्स-4-16/1(489)/2015 दिनांक 22.12.2016 द्वारा प्राप्त। मार्ग के संरेखण में ग्रामीणों द्वारा विवाद को समाप्त कर 2.00 कि0मी0 में पहाड़ कटान एवं पार्ट-।। का कार्य पूर्णं, दायित्वों का भुगतान शेष। वन भूमि पेकेज संख्या:- एफ.पी./यू.के./ रोड़/12421/2015 -- as on 31-Jan-2023
Physical Peramenters