Work Profile Report [38W282]

नौटी - छातोली मोटर मार्ग का जखेट तक विस्तार कि0मी0 4.00 से 8.00 तक
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0:- 4305/।।।(2)/11-16 (मु0मं0घो0) / 2011 दिनांक 16.09.2011

TS Amount (lakhs) : 2.68 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

50.32

Resanction Cost :

50.32

Tentative Cost :

24.72

Saving

25.60

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

50.32

Demand :

10.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Survey work done

Sanction on : 14 years 2 months ago

16 Sep 2011

Physical Progress:

At start of FY 2025-2026 :

80 %

Up to Date :

60 %

Tentative Completion date on : 1 year 3 months from now

31 Mar 2027

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
4
4
4
-

Remark

view all

Overall Saving 25.6 has been recorded as expected cost of work reduced from 50.32 to 24.72 . -- as on 07-Dec-2025

Rating : 80

Forest Case Pending At : 13: AIP DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: