Work Profile Report [38W284]

चांदपुर गढ़ी से नौना पंया (पेन्था) तक मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0:- 4208/।।।(2)/11-59 (प्रा0आ0) / 2011 दिनांक 19.09.2011

TS Amount (lakhs) : 11.09 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

90.00

Resanction Cost :

90.00

Tentative Cost :

45.20

Saving

44.80

Exp. Upto Last Fy :

18.08

For CFY 2025-2026

Remaining :

71.92

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

18.08

Work completed

Sanction on : 14 years 3 months ago

19 Sep 2011

Physical Progress:

At start of FY 2025-2026 :

80 %

Up to Date :

80 %

Tentative Completion date on : 2 years 2 months from now

31 Mar 2028

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
7
7
7
-
Bridge
1 (30m)
1 (30m)
1 (30m)
-

Remark

view all

यूटिलिटि सिफ्टिंग क्षतिपूर्ति वृक्षारोपण आदि का व्यय नहीं किया जाना है। -- as on 31-Dec-2025

Rating : 80

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: