Work Profile Report [38W392]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. 5570/।।।(2)/14-27(प्रा.आ.)/2014 दि. 19.11.2014
TS Amount (lakhs) : 16.71 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
42.51
Resanction Cost :
42.51
Tentative Cost :
34.81
Saving
7.70
Exp. Upto Last Fy :
14.81
For CFY 2025-2026
Remaining :
27.70
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
14.81
Work completed
Sanction on : 11 years 2 months ago
19 Nov 2014
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 6 months 1 week from now
31 Jul 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मुआवजा बांटा जाना है। पी0एम0जी0एस0वाई0 फेज 4 में प्रस्तावित -- as on 03-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: