Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
38W449 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं.:- 2379/।।।(2)/16-06(एम0एल0ए0)/ 2015 दिनांक 31.08.2016
TS Amount (lakhs) : 246.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
255.19
Resanction Cost :
255.19
Tentative Cost :
255.19
Exp. Upto Last Fy : 240.11
For CFY 2024-2025
Remaining : 15.08
Demand : 3.80
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 240.11
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 years 10 months ago
31 Aug 2016
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.00 कि.मी. में पहाड़ कटान एवं ं पार्ट-।। का कार्य पूर्ण। सोलिंग कार्य पूर्ण। -- as on 31-Jul-2020
Physical Peramenters