Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 1.8 | 1.8 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 30 | 30 | 30 | 0 |
38W484 :
Administrative Approval Detail : शा.सं.:- 1623/।।।(2)/17-06(एम0एल0ए0)/ 2017 टी0सी0 दिनांक 03.08.2017
TS Amount (lakhs) : 250.64 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
250.64
Resanction Cost :
250.64
Tentative Cost :
250.64
Exp. Upto Last Fy : 245.84
For CFY 2024-2025
Remaining : 4.80
Demand : 0.27
Allotment : 0.00
Exp in CFY : 0.27
Total Up to Date Exp : 246.11
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 11 months ago
03 Aug 2017
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.80 कि0मी0 में पहाड़ कटान एवं पार्ट-ं।। का कार्य पूर्ण। नाली निर्माण कार्य प्रगति में। सोलिंग कार्य 200 मीटर में पूर्ण। 30 मी0 स्पान मोटर सेतु माह 11/2019 में पूर्ण। -- as on 03-Mar-2022
Physical Peramenters