Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 1.200 |
38W631 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाइल संख्या:- 45355 लोक निर्माण अनुभाग-2 देहरादून दिनांक 28.03.2023
TS Amount (lakhs) : 210.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
105.42
Resanction Cost :
105.42
Tentative Cost :
105.42
Exp. Upto Last Fy : 31.65
For CFY 2024-2025
Remaining : 73.77
Demand : 65.00
Allotment : 35.00
Exp in CFY : 33.62
Total Up to Date Exp : 65.27
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
4 days 4 hours ago
13 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर नाली, दीवार, जी-1, जी-2, जी-3, व पी0सी0 का कार्य पूर्ण। पैरापिट, रोड फर्नीचर आदि का कार्य शेष। -- as on 28-Jun-2024
Physical Peramenters