Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
38W638 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 121291/01 (07)/2020- E-37777/2023
TS Amount (lakhs) : 497.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
497.87
Resanction Cost :
497.87
Tentative Cost :
497.87
Exp. Upto Last Fy : 7.96
For CFY 2024-2025
Remaining : 489.91
Demand : 190.48
Allotment : 0.00
Exp in CFY : 185.52
Total Up to Date Exp : 193.48
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 60 %
Sanction on :
1 year 2 months ago
15 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 01-Jun-2024
Physical Peramenters