Administrative Approval Detail : 121291/01 (07)/2020- E-37777/2023
TS Amount (lakhs) : 497.87 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
497.87
Resanction Cost :
497.87
Tentative Cost :
497.87
Exp. Upto Last Fy :
444.56
For CFY 2025-2026
Remaining :
53.31
Demand :
18.98
Allotment :
18.98
Exp in CFY :
18.98
Total Up to Date Exp :
463.54
Work completed
Sanction on : 2 years 7 months ago
15 May 2023
Physical Progress:
At start of FY 2025-2026 :
70 %
Up to Date :
100 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नवीनीकरण एवं पार्किंग का कार्य दिनांक 1/10/2024 में पूर्ण। -- as on 02-Dec-2025