Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 2.000 |
38W670 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : e-file no. 54566
TS Amount (lakhs) : 135.05 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
135.05
Resanction Cost :
135.05
Tentative Cost :
135.05
Exp. Upto Last Fy : 46.87
For CFY 2024-2025
Remaining : 88.18
Demand : 88.00
Allotment : 23.70
Exp in CFY : 59.06
Total Up to Date Exp : 105.93
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 85 %
Sanction on :
1 year 3 days ago
14 Jul 2023
Tentative Completion date:
1 month 4 days from now
22 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग पर नाली, दीवार, जी-1, जी-2, जी-3, व पी0सी0 का कार्य पूर्ण। पैरापिट, रोड फर्नीचर आदि का कार्य शेष। -- as on 28-Jun-2024
Physical Peramenters