Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 |
38W679 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 5347/।।।(2)/2023-01 (प्रा0आ0)/2023 दि0 05/12/2023
TS Amount (lakhs) : 118.07 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
118.11
Resanction Cost :
118.11
Tentative Cost :
118.11
Exp. Upto Last Fy : 53.36
For CFY 2024-2025
Remaining : 64.75
Demand : 64.75
Allotment : 50.00
Exp in CFY : 0.00
Total Up to Date Exp : 53.36
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
7 months 1 week ago
05 Dec 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 02-Jul-2024
Physical Peramenters