Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 2.5 | 2.5 | 0 |
38W70 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0ः-3174/।।।-2/06-32 (प्रा0आ0)/06 दि0 27.11.2006
TS Amount (lakhs) : 168 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
168.00
Resanction Cost :
168.00
Tentative Cost :
168.00
Exp. Upto Last Fy : 168.10
For CFY 2024-2025
Remaining : -0.10
Demand : 15.00
Allotment : 1.00
Exp in CFY : 0.27
Total Up to Date Exp : 168.37
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
17 years 7 months ago
27 Nov 2006
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: Sanction Required form Govt
वन भूमि की सै0 स्वी0 भा0स0 के प. 8बी0/यू0सी0पी0/06/229/2015 /एफ0सी0/1420 दि0 12.10.2018 द्वारा प्राप्त। एन.पी.वी. रु0 58.14 लाख भुगतान। आख्या माह 06/2019 द्वारा भारत सरकार को प्रेषित। छपान कार्य पूर्ण। म्यूटेशन की कार्यवाही पूर्ण कर अनुपालन वन निगम को कटान एवं ढुलान हेतु रु0 10.58 लाख का भुगतान दि0 23.10.2019 को किया जा चुका है।स्वीकृत लागत में 2.50 कि0मी0 में ही निर्माण कार्य हो पायेगा। 2.50 कि0मी0 में पहाड़ कटान एवं 2.30 कि0मी0 में पार्ट-।। का कार्य पूर्णं। वन भूमि पेकेज संख्या:- एफ.पी./यू.के./ रोड़/10925/2015 -- as on 31-Jan-2023
Physical Peramenters