Work Profile Report [38W730]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-file No. 52001 Dt. 04/12/2024
TS Amount (lakhs) : 71.34 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
71.34
Resanction Cost :
71.34
Tentative Cost :
71.25
Saving
0.09
Exp. Upto Last Fy :
20.35
For CFY 2025-2026
Remaining :
50.99
Demand :
50.90
Allotment :
42.65
Exp in CFY :
24.32
Total Up to Date Exp :
44.67
Work completed
Sanction on : 1 year 1 week ago
04 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 week from now
24 Jan 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 0.09 has been recorded as expected cost of work reduced from 71.34 to 71.25 . -- as on 08-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: