Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 8.37 | 8.120 | 0.25 | 0.000 | 0.250 |
38W79 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0ः-764/।।।(2)/08-65 (प्रा0आ0)/07 दि0 24.3.08
TS Amount (lakhs) : 487.49 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
551.25
Resanction Cost :
551.25
Tentative Cost :
551.25
Exp. Upto Last Fy : 476.00
For CFY 2024-2025
Remaining : 75.25
Demand : 11.00
Allotment : 5.00
Exp in CFY : 0.00
Total Up to Date Exp : 476.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
3 months 1 week ago
10 Apr 2024
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
पार्ट-। एवं पार्ट-।। का कार्य पूर्ण। -- as on 04-Jul-2024
Physical Peramenters