Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 35 | 35 | 7.500 | 27.5 | 27.500 | 1.000 |
39W1002 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 806.9 Lacs
Financial Detail
Sanction Cost : 806.90 Lacs
Resanction Cost : 806.90 Lacs
Exp. Upto Last Fy : 124.35 Lacs
For CFY 2024-2025
Remaining : 682.55 Lacs
Demand : 682.56 Lacs
Allotment : 200.00 Lacs
Exp in CFY : 122.97 Lacs
Total Up to Date Exp : 247.32 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
8.50 किमी0 में BM & SDBC का कार्य पूर्ण। शेष कार्य प्रगति में। -- as on 01-May-2024
Physical Peramenters