Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 13.5 | 13.5 | 1.500 | 12 | 12.000 | 0.000 |
39W1003 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 322.32 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
322.32
Resanction Cost :
322.32
Tentative Cost :
322.32
Exp. Upto Last Fy : 25.79
For CFY 2024-2025
Remaining : 296.53
Demand : 296.53
Allotment : 150.00
Exp in CFY : 2.16
Total Up to Date Exp : 27.95
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.50 किमी0 में SDBC कार्य पूर्ण। -- as on 31-Mar-2024
Physical Peramenters