Work Profile Report [39W1003]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 322.32 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
322.32
Resanction Cost :
322.32
Tentative Cost :
322.32
Exp. Upto Last Fy :
25.79
For CFY 2024-2025
Remaining :
296.53
Demand :
296.53
Allotment :
5.00
Exp in CFY :
2.16
Total Up to Date Exp :
27.95
Construction Started
Sanction on : 1 year 6 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
40 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
1.50 किमी0 में SDBC कार्य पूर्ण। -- as on 31-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand