Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.98 | 9.98 | 0.000 | 9.98 | 4.000 | 2.500 |
39W1004 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 251.69 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
251.69
Resanction Cost :
251.69
Tentative Cost :
251.69
Exp. Upto Last Fy : 52.33
For CFY 2024-2025
Remaining : 199.36
Demand : 105.00
Allotment : 75.00
Exp in CFY : 53.18
Total Up to Date Exp : 105.51
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 90 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.50 किमी0 में पीसी द्वारा अनुरक्षण का कार्य पूर्ण। दीवार एवं नाली निर्माण का कार्य प्रगति में। -- as on 24-Jun-2024
Physical Peramenters