Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.98 | 9.98 | 0.000 | 9.98 | 4.000 | 0.000 |
39W1004 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 251.69 Lacs
Financial Detail
Sanction Cost : 251.69 Lacs
Resanction Cost : 251.69 Lacs
Exp. Upto Last Fy : 52.33 Lacs
For CFY 2024-2025
Remaining : 199.36 Lacs
Demand : 105.00 Lacs
Allotment : 75.00 Lacs
Exp in CFY : 15.61 Lacs
Total Up to Date Exp : 67.94 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मोटर मार्ग के वासआउट /दलदली भागों में जी-1 का कार्य एवं वायरक्रेट द्वारा दीवार निर्माण आदि का कार्य प्रगति में। -- as on 13-Dec-2023
Physical Peramenters