Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9 | 0.000 | 9 | 9.000 | 8.500 |
39W1008 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 130.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
130.35
Resanction Cost :
130.35
Tentative Cost :
130.35
Exp. Upto Last Fy : 34.80
For CFY 2024-2025
Remaining : 95.55
Demand : 95.55
Allotment : 50.00
Exp in CFY : 76.02
Total Up to Date Exp : 110.82
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
8.50 किमी0 में पीसी का कार्य पूर्ण। -- as on 24-Jun-2024
Physical Peramenters