Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
39W1020 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी रूद्रप्रयाग का पत्र संख्या 213/जि0यो0/2023 दिनांक 28.06.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.00
Resanction Cost :
4.00
Tentative Cost :
4.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 4.00
Demand : 3.65
Allotment : 3.65
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
1 year 2 weeks ago
28 Jun 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पैदल मार्ग का निर्माण कार्य प्रगति में। -- as on 25-Apr-2024
Physical Peramenters