Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.3 | 3.3 | 0.000 | 3.3 | 3.300 | 3.300 |
39W1026 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/41204/2023 ई-फाइल सं0-50408 लोक निर्माण अनुभाग-2 दिनांक 27.07.2023
TS Amount (lakhs) : 222.51 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
222.78
Resanction Cost :
222.78
Tentative Cost :
222.78
Exp. Upto Last Fy : 78.67
For CFY 2024-2025
Remaining : 144.11
Demand : 144.00
Allotment : 38.51
Exp in CFY : 38.51
Total Up to Date Exp : 117.18
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 95 %
Sanction on :
11 months 2 weeks ago
27 Jul 2023
Tentative Completion date:
1 month 2 weeks from now
07 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.30 किमी0 में PC कार्य पूर्ण।
नाली निर्माण, पैरापिट, साइनबोर्ड, किमी0 स्टोन का कार्य प्रगति मंे। दायित्व शेष।
-- as on 25-Jun-2024
Physical Peramenters