Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 1.8 | 0.000 | 1.8 | 0.000 | 0.000 |
39W1028 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/13071/2023 ई-फाइल सं0-55041 लोक निर्माण अनुभाग-2 दिनांक 03.08.2023
TS Amount (lakhs) : 54.13 Lacs
Financial Detail
Sanction Cost : 54.13 Lacs
Resanction Cost : 54.13 Lacs
Exp. Upto Last Fy : 0.71 Lacs
For CFY 2024-2025
Remaining : 53.42 Lacs
Demand : 53.00 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.71 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
9 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान कार्य प्रगति में। -- as on 31-Mar-2024