Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 1.8 | 0.000 | 1.8 | 0.000 | 0.000 |
39W1028 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/13071/2023 ई-फाइल सं0-55041 लोक निर्माण अनुभाग-2 दिनांक 03.08.2023
TS Amount (lakhs) : 54.13 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
54.13
Resanction Cost :
54.13
Tentative Cost :
54.13
Exp. Upto Last Fy : 0.71
For CFY 2024-2025
Remaining : 53.42
Demand : 53.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.71
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 40 %
Sanction on :
11 months 2 weeks ago
03 Aug 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.00 किमी0 में पहाड कटान का कार्य पूर्ण। शेष पहाड कटान का कार्य प्रगति में। -- as on 31-May-2024
Physical Peramenters