Work Profile Report [39W104]

आश्रम से घरडा-मखेत मोटर मार्ग ग्राम कोटी तक विस्तार
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा.स. 2490/।।।-2/08-06 (प्रा0आ0)/07 दि. 25.07.08

TS Amount (lakhs) : 276.53 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

358.00

Resanction Cost :

358.00

Tentative Cost :

358.00

Exp. Upto Last Fy :

298.15

For CFY 2024-2025

Remaining :

59.85

Demand :

4.90

Allotment :

2.40

Exp in CFY :

0.00

Total Up to Date Exp :

298.15

Construction Started

Sanction on : 16 years 3 months ago

25 Jul 2008

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
6.000
0
0.000
0.000
Bridge
1 (45m)
1 (45m)
0 (0.000m)
1 (45m)
0 (0.000m)
0 (0.000m)

Remark

view all

मार्ग निर्माण कार्य पूर्ण। सेतु के डिजाइन हेतु कार्यवाही गतिमान। -- as on 14-Jul-2024

Rating : 87

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand