Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6.000 | 0 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 45 | 45 | 0.000 | 45 | 0.000 | 0.000 |
39W104 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.स. 2490/।।।-2/08-06 (प्रा0आ0)/07 दि. 25.07.08
TS Amount (lakhs) : 276.53 Lacs
Financial Detail
Sanction Cost : 358.00 Lacs
Resanction Cost : 358.00 Lacs
Exp. Upto Last Fy : 298.15 Lacs
For CFY 2024-2025
Remaining : 59.85 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 298.15 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
15 years 9 months ago
25 Jul 2008
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग निर्माण कार्य पूर्ण। सेतु निर्माण हेतु निविदा आमंत्रण की कार्यवाही की जा रही है। -- as on 30-Nov-2021
Physical Peramenters