Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15.35 | 15.35 | 0.000 | 15.35 | 15.350 | 15.350 |
39W1070 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 185624/2024 ई पत्रावली संख्या 48456 लोक निर्माण अनुभाग दिनांक 30.01.2024
TS Amount (lakhs) : 276.72 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
276.72
Resanction Cost :
276.72
Tentative Cost :
276.72
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 276.72
Demand : 276.72
Allotment : 150.00
Exp in CFY : 165.64
Total Up to Date Exp : 165.64
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 80 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
15.35 किमी0 में पीसी कार्य पूर्ण। शेष दीवार एवं नाली निर्माण का कार्य प्रगति में। -- as on 24-Jun-2024
Physical Peramenters