Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 28 | 28 | 0.000 | 28 | 28.000 | 0.000 |
39W1072 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 256/।।।(3)/2024-01(CRIF)/2022 दिनांक 29.02.2024 एवं उत्तराखण्ड शासन के पत्र संख्या 322/।।।(3)/2024-14 (CRIF)/2024 दिनांक 16.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 2,083.11 Lacs
Resanction Cost : 2,083.11 Lacs
Exp. Upto Last Fy : 90.00 Lacs
For CFY 2024-2025
Remaining : 1,993.11 Lacs
Demand : 1,993.11 Lacs
Allotment : 500.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 90.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
2 months 3 days ago
16 Mar 2024
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Scupper, Corner cutting एवं दीवार निर्माण का कार्य प्रगति में। -- as on 01-May-2024
Physical Peramenters