Administrative Approval Detail : जिलाधिकारी का पत्र संख्या 13/जि0यो0-03/(अर्थ एवं संख्या) /2024-25 दिनांक 20.07.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7.00
Resanction Cost :
7.00
Tentative Cost :
7.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
7.00
Demand :
3.50
Allotment :
3.50
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Technical sanction done
Sanction on : 4 months 3 days ago
20 Jul 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 year 4 months from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 7 has been counted as tentative cost increased from to 7 . निविदा की कार्यवाही गतिमान। -- as on 20-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: