Work Profile Report [39W1129]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. ।/239943/2024 ई-फाईल सं0 54684 /लोक निर्माण अनुभाग-2 दिनांक 13.09.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
97.52
Resanction Cost :
97.52
Tentative Cost :
97.52
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
97.52
Demand :
75.67
Allotment :
50.00
Exp in CFY :
15.07
Total Up to Date Exp :
15.07
Construction Started
Sanction on : 3 months 1 week ago
13 Sep 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 year 3 months from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Excess requirement 97.52 has been counted as tentative cost increased from to 97.52 .
सुपर एलीवेशन एवं सोलिग कोट हेतु पत्थर एकत्रीकरण का कार्य प्रगति में।
-- as on 02-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: