Work Profile Report [39W117]

fघमतोली-स्वारी-ग्वांस मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा.सं. 3109/।।।-2/06-68(प्रा0आ0) /6 दि. 23.11.06

TS Amount (lakhs) : 84 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

84.00

Resanction Cost :

84.00

Tentative Cost :

84.00

Exp. Upto Last Fy :

67.96

For CFY 2024-2025

Remaining :

16.04

Demand :

16.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

67.96

Construction Started

Sanction on : 18 years 16 hours ago

23 Nov 2006

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
3.2
0.000
3.2
0.000
0.000

Remark

view all

2 किमी0 में पहाड कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 30-Aug-2023

Rating : 84

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: