Work Profile

39W117 :

No Pic Avilable Time series Gantt
fघमतोली-स्वारी-ग्वांस मोटर मार्ग


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा.सं. 3109/।।।-2/06-68(प्रा0आ0) /6 दि. 23.11.06

TS Amount (lakhs) : 84 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

84.00

Resanction Cost :

84.00

Tentative Cost :

84.00

Exp. Upto Last Fy : 67.96

For CFY 2024-2025

Remaining : 16.04

Demand : 16.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 67.96

Construction Started

Physical Progress:

At start of FY 2024-2025 : 80 %

Up to Date : 80 %

Sanction on :
17 years 7 months ago
23 Nov 2006


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 88

Remark

Bottelneck: no issue


2 किमी0 में पहाड कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 30-Aug-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 5 3.2 0.000 3.2 0.000 0.000
Currently only Bank Gaurantee information is avilable