Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 3.2 | 0.000 | 3.2 | 0.000 | 0.000 |
39W117 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 3109/।।।-2/06-68(प्रा0आ0) /6 दि. 23.11.06
TS Amount (lakhs) : 84 Lacs
Financial Detail
Sanction Cost : 84.00 Lacs
Resanction Cost : 84.00 Lacs
Exp. Upto Last Fy : 67.96 Lacs
For CFY 2024-2025
Remaining : 16.04 Lacs
Demand : 16.00 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 67.96 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
17 years 5 months ago
23 Nov 2006
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2 किमी0 में पहाड कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 30-Aug-2023
Physical Peramenters