Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
39W221 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सख्ंया 5157/।।।(2)/10-05 (मु0मं0घो0)/2010 दिनांक 9.11.2010
TS Amount (lakhs) : 59.9 Lacs
Financial Detail
Sanction Cost : 126.00 Lacs
Resanction Cost : 126.00 Lacs
Exp. Upto Last Fy : 71.05 Lacs
For CFY 2024-2025
Remaining : 54.95 Lacs
Demand : 15.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 71.05 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
13 years 6 months ago
09 Nov 2010
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
भारत सरकार के पत्र संख्या 8बी/यूसीपी/06/36/2020/एफसी/537 दिनांक 14.07.2022 द्वारा विधिवत स्वीकृति प्राप्तं द्वितीय चरण की स्वीकृति के अन्तर्गत कार्य प्रगति पर है। -- as on 30-Aug-2023
Physical Peramenters