Work Profile Report [39W222]

मा0 मुख्यमंत्री घोषणा 2010 के अन्तर्गत- कोटली-बांसी-सेरा मोटर मार्ग (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शासनादेश सख्ंया 5157/।।।(2)/10-05 (मु0मं0घो0)/2010 दिनांक 9.11.2010

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

100.80

Resanction Cost :

100.80

Tentative Cost :

100.80

Exp. Upto Last Fy :

0.10

For CFY 2024-2025

Remaining :

100.70

Demand :

1.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.10

Construction Started

Sanction on : 14 years 1 month ago

09 Nov 2010

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

80 %

Tentative Completion date on : 3 months 6 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
8
8
0.000
8
0.000
0.000

Remark

view all

भारत सरकार के पत्र संख्या 8बी/यूसीपी/06/91/2012/एफसी/2714 दिनांक 31.03.2016 द्वारा आॅफ लाइन (Offline) विधिवत स्वीकृति प्राप्त। द्वितीय चरण की स्वीकृति के अन्तर्गत कार्य प्रगति पर है। -- as on 26-Dec-2023

Rating : 83

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: