Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
39W222 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सख्ंया 5157/।।।(2)/10-05 (मु0मं0घो0)/2010 दिनांक 9.11.2010
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
100.80
Resanction Cost :
100.80
Tentative Cost :
100.80
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 100.70
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
13 years 8 months ago
09 Nov 2010
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
भारत सरकार के पत्र संख्या 8बी/यूसीपी/06/91/2012/एफसी/2714 दिनांक 31.03.2016 द्वारा आॅफ लाइन (Offline) विधिवत स्वीकृति प्राप्त। द्वितीय चरण की स्वीकृति के अन्तर्गत कार्य प्रगति पर है। -- as on 26-Dec-2023
Physical Peramenters