Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
39W223 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 6985/।।।(2)/10-18(प्रा0आ0)/2010 टी0सी0-4 दिनांक 03.02.2011
TS Amount (lakhs) : 14.47 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy : 20.52
For CFY 2024-2025
Remaining : 17.28
Demand : 17.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 20.52
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
13 years 5 months ago
03 Feb 2011
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण के अन्तर्गत कार्य पूर्ण। मुआवजा वितरण शेष है। -- as on 30-Mar-2022
Physical Peramenters