Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 0.000 | 2.5 | 0.000 | 0.000 |
39W316 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी का पत्र संख्या 532/fजला योजना /अर्थ एवं संख्या/लो0fन0fव0 /12-13 fदनांक 11.09.2012
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
31.50
Resanction Cost :
31.50
Tentative Cost :
31.50
Exp. Upto Last Fy : 0.53
For CFY 2024-2025
Remaining : 30.97
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.53
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
11 years 10 months ago
11 Sep 2012
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 07: Nodal
Bottelneck: no issue
संशोधित समरेखण अनुमोदित कर पत्रावली पुनः अपलोड कर दी गयी है। उप वन संरक्षक रूद्रप्रयाग के पत्र संख्या 3947/12-1(2) दिनांक 19.06.2024 द्वारा आपत्तियों का निराकरण कर पत्रावली नोडल अधिकारी को प्रेषित। -- as on 24-Jun-2024
Physical Peramenters