Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
39W364 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3698(1)/।।।(2)/12-04(मु0मं0घो0) /2012 दिनांक 18.10.2012
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 63.00 Lacs
Resanction Cost : 63.00 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 63.00 Lacs
Demand : 0.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
11 years 7 months ago
18 Oct 2012
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: Alignment Dispute
वनभूमि की गठित पूर्व पत्रावली निरस्त। नापखेत में ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 30-Dec-2023
Physical Peramenters