Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 0.000 | 0.000 |
39W380 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3698(1)/।।।(2)/12-04(मु0मं0घो0) /2012 दिनांक 18.10.2012
TS Amount (lakhs) : 8.59 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
12.60
Resanction Cost :
12.60
Tentative Cost :
12.60
Exp. Upto Last Fy : 5.86
For CFY 2024-2025
Remaining : 6.74
Demand : 1.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.86
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
11 years 8 months ago
18 Oct 2012
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
भारत सरकार के पत्र संख्या 8बी/यूसीपी/06/274/2015/एफ0सी0/1001 दिनांक 19.08.2020 द्वारा विधिवत स्वीकृति प्राप्त। एनपीवी की धनराशि जमा की जा चुकी है। द्वितीय चरण की स्वीकृति के अन्तर्गत कार्य प्रगति पर है। -- as on 26-Dec-2023
Physical Peramenters