Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 0.000 | 0.000 |
39W40 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 1080/111(2)/07-97 (प्रा0आ0)/05 दि0 17.05.07
TS Amount (lakhs) : 67.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
67.20
Resanction Cost :
67.20
Tentative Cost :
67.20
Exp. Upto Last Fy : 24.88
For CFY 2024-2025
Remaining : 42.32
Demand : 40.00
Allotment : 4.73
Exp in CFY : 4.73
Total Up to Date Exp : 29.61
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
17 years 2 months ago
17 May 2007
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
भारत सरकार के पत्र संख्या 8बी/यूसीपी/06/91/2012/एफसी/2714 दिनांक 31.03.2016 द्वारा आॅफ लाइन (Offline) विधिवत स्वीकृति प्राप्त।
1.50 िकमी0 में पहाड कटान कार्य पूर्ण। शेष कार्य प्रगति में।
-- as on 26-Dec-2023
Physical Peramenters