Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
39W495 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4520/।।।(2)/15-08(मु.मं.घो.)/2015 दिनांक 19.06.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.86
Resanction Cost :
37.86
Tentative Cost :
37.86
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 37.86
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
9 years 4 weeks ago
19 Jun 2015
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वे इत्यादि कार्य हेतु निविदा आमंत्रित की गयी हैं। ग्रामीणों से NOC अपेक्षित है। -- as on 30-Aug-2023
Physical Peramenters