Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
39W537 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी का पत्र संख्या 505/fवfवध/2015-16 fदनांक 08.02.2016
TS Amount (lakhs) : 1.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 37.80
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
8 years 5 months ago
08 Feb 2016
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 11: AIP Division
Bottelneck: no issue
भारत सरकार के पत्र संख्या 8बी/यूसीपी/06/129/2021/एफसी/734 दिनांक 26.08.2022 द्वारा सैद्धान्तिक स्वीकृति प्राप्त। एनपीवी की धनराशि जमा कर दी गयी है। अनुपालन आख्या इस कार्यालय के पत्र संख्या 1162/16सी दिनांक 11.04.2023 द्वारा प्रेषित। डीएफओ के पत्र संख्या 1042/12-1(2) दिनांक 20.09.2023 द्वारा कार्य करने की अनुमति प्राप्त है। डीएफओ द्वारा क्षतिपूरक वृक्षारोपण के मानचित्र व केएमएल फाइल चाही गयी है, जिस हेतु इस कार्यालय के पत्र संख्या 80/16सी दिनांक 09.01.2024 द्वारा आई टी सैल देहरादून को पत्र लिखा गया है। -- as on 09-Jan-2024
Physical Peramenters