Work Profile Report [39W576]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : fजलाfधकारी का पत्र संख्या 483/fजला योजना /अर्थ एवं संख्या/लो0fन0fव0/2016-17 fदनांक 30.11.2016
TS Amount (lakhs) : 23.52 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
26.00
Resanction Cost :
26.00
Tentative Cost :
26.00
Exp. Upto Last Fy :
7.74
For CFY 2024-2025
Remaining :
18.26
Demand :
18.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
7.74
Construction Started
Sanction on : 7 years 11 months ago
30 Nov 2016
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 31-Jul-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI: