Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
39W600 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3259/।।। (2)/16-48 (प्रा0आ0)/2016 दिनांक 29.12.2016
TS Amount (lakhs) : 4.08 Lacs
Financial Detail
Sanction Cost : 32.16 Lacs
Resanction Cost : 32.16 Lacs
Exp. Upto Last Fy : 2.10 Lacs
For CFY 2024-2025
Remaining : 30.06 Lacs
Demand : 0.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.10 Lacs
Survey work done
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
7 years 4 months ago
29 Dec 2016
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वे कार्य पूर्ण। संरेखण आख्या वृत्तीय कार्यालय के पत्र संख्या 2599/39याता-7/2023 दिनांक 22.05.2023 द्वारा अनुमोदित। वन वन विभाग से संयुक्त निरीक्षण आख्या प्राप्त। डिजिटल मानचित्र बनाये जा रहे हैं। तदोपरान्त ही वनभूमि हस्तान्तरण की कार्यवाही की जायेगी। -- as on 17-Jan-2024
Physical Peramenters