Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
39W601 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3277/।।।(2)/17-18(प्रा0आ0) /2010 टीसी-चार दिनांक 03.01.2017
TS Amount (lakhs) : 151.28 Lacs
Financial Detail
Sanction Cost : 151.28 Lacs
Resanction Cost : 151.28 Lacs
Exp. Upto Last Fy : 124.42 Lacs
For CFY 2024-2025
Remaining : 26.86 Lacs
Demand : 26.00 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 2.50 Lacs
Total Up to Date Exp : 126.91 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 years 4 months ago
03 Jan 2017
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 किमी0 में पहाड कटान व दीवार निर्माण कार्य पूर्ण। दायित्व शेष। -- as on 21-Nov-2023
Physical Peramenters