Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.250 | 0.25 | 0.000 | 0.000 |
39W611 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी का पत्र संख्या 454 /fजला योजना /अर्थ एवं संख्या /लो0fन0fव0/2017-18 fदनांक 08.11.2017
TS Amount (lakhs) : 17.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.35
Resanction Cost :
17.35
Tentative Cost :
17.35
Exp. Upto Last Fy : 16.61
For CFY 2024-2025
Remaining : 0.74
Demand : 0.74
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 16.61
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
6 years 8 months ago
08 Nov 2017
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 28-Apr-2022
Physical Peramenters